Project Overview
This project involves the Supply, Erection, Testing, and Commissioning of a 132 kV Single Circuit Gondal–Haripur LILO (Line-In Line-Out) at the 220 kV Visavadar Substation. Designed to strengthen GETCO’s transmission network, the project enhances reliability, improves load management, and ensures efficient power evacuation within the region. The 18.96 KM LILO line plays a key role in supporting non-renewable power distribution across Visavadar and surrounding areas.
Project Snapshot
Client: GETCO
Location: Visavadar, Gujarat
Start Date: 02.06.2017
Completion Date: 30.05.2025
Line Length: 18.96 KM
Sector: Non-Renewable
Project Authority: C.E. PROJECT – GETCO
Scope of Work
-
Survey, supply, and erection of 132 kV S/C transmission line on approved tower structures.
-
Stringing of conductors, OPGW installation, and hardware fitting.
-
Testing and commissioning as per GETCO technical standards.
-
Foundation work, tower erection, and alignment correction.
-
Ensuring compliance with safety, quality, and statutory norms.
-
Coordination for Right of Way (ROW) and clearances.
Challenges
-
Extended project timeline due to land clearance delays and stakeholder coordination.
-
Ensuring safe working conditions across uneven terrain and agricultural zones.
-
Managing logistics for tower materials during seasonal constraints.
-
Adhering to updated GETCO testing protocols during long project duration.
Solution
-
Carried out phased execution to align with ROW availability and site readiness.
-
Deployed experienced teams for rapid erection and quality-controlled stringing.
-
Strengthened site logistics with optimized material movement planning.
-
Implemented continuous safety training and testing workflows to maintain standards.
Success Story
Despite challenging timelines and terrain complexities, the project progressed with steady momentum through efficient planning and expert execution. The successful erection and commissioning of the 18.96 KM 132 kV LILO line significantly enhances power stability around Visavadar. The project stands as a testament to strong collaboration between field teams, engineers, and GETCO leadership.
Key Highlights
-
Construction of 18.96 KM, 132 kV S/C LILO line integrated into GETCO’s 220 kV Visavadar network.
-
Enhanced transmission reliability for critical non-renewable power corridors.
-
Strong coordination with local authorities ensuring smooth ROW management.
-
Delivered with high safety, precision, and adherence to GETCO specifications.
-
Reinforces GETCO’s long-term plan to strengthen Gujarat’s state grid infrastructure.