Project Overview

This project focuses on the Supply, Erection, Testing, and Commissioning of a 132 kV Single Circuit Junagadh–Talala LILO (Line-In Line-Out) at the 220 kV Shapur Substation. Designed to improve grid reliability and ensure steady power flow in the region, this 11.95 KM transmission line strengthens GETCO’s non-renewable energy transmission network and enhances operational efficiency.

##Project Snapshot

Client: GETCO

Location: Shapur, Gujarat

Start Date: 02.05.2017

Completion Date: 15.06.2020

Line Length: 11.95 KM

Sector: Non-Renewable

Project Authority: C.E. PROJECT – GETCO

Scope of Work

  • Execution of 132 kV S/C LILO transmission line connecting Junagadh–Talala via the Shapur substation.

  • Complete material supply, tower erection, and foundation construction.

  • Stringing of conductors, OPGW cable installation, and hardware fittings.

  • Testing and commissioning as per GETCO technical standards.

  • Compliance with safety protocols, ROW management, and statutory requirements.

Challenges

  • Navigating agricultural landscapes and obtaining ROW permissions in densely cultivated areas.

  • Managing material transport and erection sequences during monsoon periods.

  • Ensuring coordination across multiple stakeholders within restricted timelines.

  • Maintaining safety and quality while working across uneven terrain.

Solution

  • Conducted phased construction aligned with ROW approvals and weather conditions.

  • Implemented efficient logistics planning for tower material movement and installation.

  • Deployed skilled erection and stringing teams with strict adherence to GETCO standards.

  • Strengthened communication between field teams, engineers, and stakeholders for smooth execution.

Success Story

The successful completion of the 11.95 KM 132 kV Junagadh–Talala LILO line significantly enhanced the stability and resilience of GETCO’s transmission network. Delivered within expected quality and safety benchmarks, the project ensured improved load management and uninterrupted power supply for the Shapur region.

Key Highlights

  • Execution of a 132 kV S/C LILO line spanning 11.95 KM.

  • Integrated seamlessly into the 220 kV Shapur Substation network.

  • Strengthened non-renewable power transmission reliability in the region.

  • Effective ROW management and phased construction ensured smooth progress.

  • Delivered with strict adherence to quality, safety, and GETCO technical guidelines.