Project Overview

This project involved the erection, testing, and commissioning of a 220kV Double Circuit transmission line from the existing 400kV GETCO Hadala Substation to the proposed 220kV Wind Farm Substation at Virva Village. Executed for Kintech Synergy Pvt. Ltd., the line plays a crucial role in enabling renewable energy evacuation from the Virva wind power project into the grid. The work required rapid execution, ROW/WLC management, and strong coordination to meet the accelerated timelines.

Project Snapshot

Client: Kintech Synergy Pvt. Ltd.

Location: Rajkot, Gujarat

Project Type: Transmission Line – Wind Power Evacuation

Voltage Level: 220kV

Route Length: 16.96 KM

Executed Length: 3.91 KM

Start Date: 10.11.2018

Completion Date: 28.02.2019

Sector: Renewable

Project Incharge: Project Manager - Kintech

Scope of Work

  • Surveying and finalization of the 220kV D/C transmission line route

  • Managing Right of Way (ROW) and Way Leave Clearance (WLC)

  • Foundation construction for multi-circuit tower structures

  • Tower erection using optimized construction methodology

  • Stringing of conductors and OPGW as required

  • Complete testing and commissioning of the newly constructed line

  • Ensuring interface compatibility with both the existing 400kV GETCO Hadala SS and the proposed 220kV Virva Wind Farm SS

Challenges

  • Tight completion timeline requiring accelerated deployment

  • ROW/WLC challenges across agricultural and privately-owned land

  • Working near existing high-voltage infrastructure with strict safety measures

  • Ensuring uninterrupted progress during peak agricultural seasons

  • Logistics coordination due to continuous material movement over distributed sites

Solution

  • Developed a fast-track execution plan aligned with Kintech’s wind project milestones

  • Dedicated teams for parallel foundation, erection, and stringing works

  • Proactive engagement with landowners to manage ROW and obtain WLC smoothly

  • Advanced safety planning to ensure error-free work around energized corridors

  • Daily coordination meetings for quick decision-making and progress optimization

Success Story

The project was completed well within the required timeframe, enabling timely power evacuation from the Virva wind farm. Seamless coordination with Kintech and GETCO allowed efficient integration of the new 220kV line with the existing grid. The successful execution enhanced system reliability and supported Gujarat’s renewable energy development initiatives.

Key Highlights

  • Successfully established a critical evacuation corridor for wind energy

  • Completed within an accelerated execution period

  • Efficient handling of ROW/WLC challenges

  • Zero safety incidents throughout the project

  • Strengthened renewable energy infrastructure in the region