Project Overview

This project involved the supply, erection, testing, and commissioning of a 220kV Double Circuit Kalavad–Kangasiyali transmission line spanning 57.465 km. The initiative aimed to enhance power transfer capability, strengthen regional grid stability, and support increasing demand across the Kalavad and Kangasiyali zones in Gujarat.

Project Snapshot

Project Name: 220kV Kalavad–Kangasiyali Transmission Line

Client: GETCO

Location: Kalavad, Gujarat

Start Date: 18.01.2019

Completion Date: 25.11.2023

Line Length: 57.46 km

Category: Non-Renewable

Project Authority: C.E. Project – GETCO

Scope of Work

  • Supply of all materials and components required for a 220kV D/C transmission line.

  • Erection of towers, stringing of AL-59 conductor, and installation of associated hardware.

  • Execution of testing and commissioning activities as per GETCO standards.

  • Ensuring right-of-way clearance, alignment approvals, and compliance with statutory norms.

  • Delivering a fully functional high-capacity transmission corridor.

Challenges

  • Challenging terrain conditions along certain stretches of the alignment.

  • Weather-related delays impacting foundation and tower erection schedules.

  • Coordination requirements across multiple villages for ROW permissions.

  • Maintaining project timelines during periods of material supply fluctuations.

Solution

  • Adopted optimized tower erection planning with staggered execution to overcome terrain issues.

  • Implemented rigorous safety and quality monitoring systems to maintain efficiency.

  • Strengthened coordination with local authorities and landowners for timely ROW clearance.

  • Deployed skilled engineering teams and advanced construction methods to ensure uninterrupted progress.

Success Story

Despite challenges in terrain, weather, and ROW management, the project was successfully completed within the revised schedule. The 220kV Kalavad–Kangasiyali line now plays a critical role in improving regional grid capacity, reducing load congestion, and supporting uninterrupted power flow for industrial and rural consumers.

Key Highlights

  • 57.465 km of 220kV Double Circuit line completed to GETCO standards.

  • Enhanced power evacuation and strengthened regional transmission network.

  • High-quality execution with minimum environmental impact.

  • Improved reliability and efficiency of the electrical grid across the Kalavad region.