Project Overview
The 220kV LILO Jetpur–Sardargadh project involved the complete Supply, Erection, Testing, and Commissioning of a 220kV LILO (Line-In Line-Out) of the 220kV S/C Jetpur–Sardargadh transmission line at the 220kV Shapur Substation. The work included construction on D/C and M/C towers using ACSR Zebra conductors and OPGW cable over a 6.20 km stretch. The project strengthened the regional transmission network and enhanced grid reliability under GETCO’s non-renewable transmission infrastructure program.
Project Snapshot
Client: GETCO Location: Shapur, Gujarat Start Date: 07.03.2019 Completion Date: 14.02.2023 Line Length: 6.20 km Route Length: 6.02 km Sector: Non-Renewable Project Lead: C.E. Project – GETCO Scope: 220kV LILO on D/C & M/C Towers with ACSR Zebra & OPGW
Scope of Work
-
Supply, erection, and stringing of 220kV transmission line on D/C & M/C towers.
-
Installation and integration of ACSR Zebra conductors for improved current carrying capacity.
-
Laying and commissioning of OPGW cable for communication and protection systems.
-
Construction of LILO arrangement at the 220kV Shapur Substation.
-
Complete testing, inspection, and commissioning as per GETCO standards.
-
Compliance with all safety, quality, and environmental guidelines.
Challenges
-
Complex tower erection in uneven and soil-variable terrain.
-
Ensuring uninterrupted grid operation during LILO integration.
-
Maintaining stringent safety protocols during high-voltage stringing.
-
Coordinating material movement and heavy equipment across narrow access routes.
-
Working under variable weather conditions affecting installation timelines.
Solution
-
Deployed a specialized team for precision tower erection and conductor stringing.
-
Used advanced tension stringing equipment to ensure safety and accuracy.
-
Implemented real-time monitoring and coordination with GETCO for outage windows.
-
Adopted optimized logistics planning for equipment movement.
-
Executed phased construction to maintain progress while managing site challenges.
Success Story
Despite technical and logistical complexities, the project was completed to GETCO’s full satisfaction. The newly commissioned 220kV LILO line significantly strengthened the regional power transmission system, reduced load on existing circuits, and enhanced network stability. Concord’s efficient planning, execution, and quality-driven approach ensured timely completion of this critical infrastructure upgrade.
Key Highlights
-
6.20 km 220kV LILO completed with precision and safety.
-
High-performance ACSR Zebra conductor and OPGW installed.
-
Successful integration with 220kV Shapur Substation.
-
Zero-accident project execution.
-
Enhanced reliability and load-handling capability of the regional grid.
-
Delivered in full compliance with GETCO’s standards and specifications.