Project Overview

The 66kV Kotda–Bavishi Transmission Line project involved the complete execution of a 3.15 km single-circuit line connecting Kotda Bavishi to the tap point of the Jamjodhpur–Vasantpur network. Concord Construction Pvt. Ltd. managed end-to-end activities including supply, erection, liaisoning, testing, and commissioning. The project strengthened local grid reliability and ensured improved power flow for Suzlon’s operational requirements in the Jamjodhpur region.

Project Snapshot

Project Name: 66kV Kotda–Bavishi Transmission Line

Client: Suzlon

Location: Jamjodhpur, Gujarat

Start Date: 15.12.2020

Completion Date: 25.06.2021

Line Length: 3.15 KM

Sector: Non-Renewable

Project Lead: Project Manager – Suzlon

Project Type: Transmission Line Project

Scope of Work

  • Supply and transportation of line materials

  • Erection of 66kV transmission towers and associated structures

  • Conductor stringing and tensioning

  • Right of Way (ROW) coordination & clearance

  • Complete liaisoning with local authorities and utilities

  • Testing and commissioning of the 66kV line up to the tap point

Challenges

  • Obtaining timely ROW clearance in active agricultural and village zones

  • Tight project schedule requiring parallel execution of civil and tower works

  • Coordination with multiple stakeholders for grid integration

  • Weather-related delays during foundation and stringing phases

Solution

  • Dedicated liaison team deployed to fast-track ROW and statutory approvals

  • Accelerated execution using additional manpower and machinery

  • Close coordination with Suzlon and government departments to avoid disruptions

  • Optimized sequencing of civil works, tower erection, and stringing to maintain schedule

Success Story

Despite ROW challenges and strict timelines, the project was completed ahead of schedule with seamless coordination between teams. The new 66kV line significantly improved connectivity for Suzlon’s renewable infrastructure, enhancing operational stability and power evacuation capacity in the Jamjodhpur area.

Key Highlights

  • End-to-end EPC execution of a 66kV transmission line

  • Smooth approval process through strategic liaisoning

  • Zero safety incidents throughout the project

  • Completed with high-quality standards and within the committed timeframe

  • Improved grid stability for Suzlon’s wind power operations