Project Overview
This project involves the complete civil construction and infrastructure development of the 220kV Bhalgamda Substation under the supervision of Kintech Synergy Pvt. Ltd. The scope includes critical civil components such as the control room building, residential quarters, and structural works essential for the substation’s operation. The project plays a key role in enhancing the state’s transmission infrastructure and ensuring reliable power delivery across the Surendranagar region.
Project Snapshot
Client: Kintech Synergy Pvt. Ltd.
End User: GETCO (Gujarat Energy Transmission Corporation Ltd.)
Project Type: EPC Civil Construction
Voltage Level: 220kV
Location: Bhalgamda, Limdi, Surendranagar
Project Duration: 12 Months
Completion Target: July 2026
Status: Planning & Mobilization Phase
Scope of Work
-
Construction of 220kV Control Room (C.R.) Building.
-
Development of T-3 and T-4 residential quarters for staff and engineers.
-
Execution of foundation works, compound wall, and cable trench construction.
-
Laying of RCC roads, parking sheds, and yard PCC with metal spreading.
-
Construction of oil sump, drainage, and other utility structures.
-
Full compliance with GETCO civil engineering and safety standards.
Chalenges
-
Managing the start of civil construction during the monsoon season.
-
Ensuring coordination between multiple work fronts (buildings, utilities, and yard areas).
-
Maintaining strict quality control and safety compliance throughout execution.
-
Timely procurement and mobilization of construction materials and heavy equipment.
Solution
-
Phased work execution plan prepared with priority scheduling for weather-sensitive tasks.
-
Dedicated on-site supervision team to monitor progress and safety adherence.
-
Coordination with GETCO’s engineering department to ensure design conformity.
-
Use of high-quality materials and durable construction practices for long-term reliability.
Success Story
The Bhalgamda Substation Civil Project is a strategic initiative supporting Gujarat’s growing energy infrastructure. By delivering modern facilities with robust design and sustainable construction methods, the project will contribute to improving power reliability and operational efficiency for the state’s grid network. The successful completion of this substation will reinforce Kintech Synergy Pvt. Ltd.’s commitment to excellence, safety, and timely delivery in every project.
Key Highlights
-
EPC civil project for 220kV substation infrastructure.
-
Enhances transmission capacity in the Surendranagar region.
-
Integrated construction of control room, staff quarters, and supporting facilities.
-
Planned and executed under strict quality and safety guidelines.
-
Designed for long-term durability and sustainability.