Project Overview

This R&M (Repair & Modernization) EPC project for Adani Cement involves the design, supply, service, installation, testing, and commissioning of two bays of a 132kV switchyard at Ambuja Nagar, along with associated works at GETCO Timbdi Substation.

The scope also includes reconductoring of the existing 12 km, 132kV Transmission Line between Timbdi and Ambuja Nagar, enhancing power transfer capacity and ensuring reliable energy supply to the cement plant operations.

Project Snapshot

Client: Adani Cement

Project Type: R&M EPC Project

Voltage Level: 132kV

Location: Ambuja Nagar & GETCO Timbdi Substation

Project Duration: 6 Months

Target Completion: February 2026

Transmission Line Length: 12 km

Status: Planning and Mobilization Stage

Scope of Work

  • Design and engineering of 132kV switchyard layout and associated control systems.

  • Supply, installation, testing, and commissioning of 2 bays of 132kV switchyard equipment.

  • Reconductoring of existing 12 km, 132kV Timbdi–Ambuja Nagar transmission line with upgraded high-efficiency conductors.

  • Integration and testing with existing GETCO grid infrastructure.

  • Comprehensive safety and quality assurance in accordance with Adani and GETCO standards.

Chalenges

  • Coordinating work between Adani Cement operations and GETCO grid infrastructure to avoid downtime.

  • Managing tight project timelines within an active industrial site.

  • Ensuring safety and minimal disruption during reconductoring of live transmission corridors.

Solution

  • Developed a phased implementation strategy to execute work with minimal impact on existing operations.

  • Deployed experienced EPC teams and advanced stringing equipment for precision and safety.

  • Used high-performance conductors and switchgear components to ensure long-term reliability and efficiency.

  • Maintained close coordination with both Adani and GETCO for seamless execution and testing.

Success Story

The 132kV Ambuja Nagar project strengthens the industrial power reliability for Adani Cement while modernizing the regional grid link with GETCO Timbdi.

Upon completion, the system will enhance transmission efficiency, reduce technical losses, and support continuous production at Adani Cement’s flagship facility—aligning with their commitment to sustainability and operational excellence.

Key Highlights

  • Dual 132kV switchyard bays installed for enhanced power reliability.

  • 12 km of 132kV line reconductored for higher load capacity.

  • Integrated design with GETCO grid systems.

  • Improved efficiency, safety, and long-term reliability of industrial power infrastructure.

  • Executed by Concord Construction Pvt. Ltd. under strict quality and safety benchmarks.